Red Eye and Widner

Red Eye Widner Banner

Project Mission

To replace approximately 1/2 mile of 2" water pipes with 6" pipes on Red Eye and Widner Circle in DeFuniak Springs, Florida and to install three new hydrants to support this neighborhood of approximately 30 homes.  Residents on these streets can expect greater water flow from their spigots beginning September 2018 and know their neighborhood is safer with fully functioning hydrants nearby.

Project Cost

  • $154,121.  
    • $93,136 of this cost will be funded through a grant from Northwest Florida Water Management District.  The City of DeFuniak Springs will contribute $75,561.

Grant Type

Reimbursement:  This grant will reimburse the City of DeFuniak Springs once approved expenditures are mat at various benchmarks of project completion from April 25, 2017 through April 25, 2019.

Grant Budget Summary

Category
Grant Funding
Site Survey$2,806
Design$5,970
Permitting$2,500
Construction$78,560
Project Management$3,300
Total
$93,136